Recent News

Micro Forests set to get bigger
Saturday, August 27, 2022

More microforests are set to appear around the island as a Bermuda Zoological Society project to plant more trees and shrubs continues to grow.


The BZS Awards Four Students Environmental Science Scholarships
Wednesday, August 24, 2022

Four Bermudian students have been awarded a combined $15,000 in educational funds as part of the Bermuda Zoological Society’s (BZS) annual BZS Steinhoff programme. Osei Agyapong, Imogen Peckett, Logan Soares and Naphisa Smith were selected for their academic achievements and their commitment to protecting the environment.


From Block Island to Montauk Through Sharks, Currents and Cramps
Tuesday, August 23, 2022

Lori King of Long Island finished a nearly 24-mile trip in 8 hours 39 minutes 45 seconds. Once her swim is certified, King will be recognized as the first person to complete the journey.


Hamilton Lions pump up the cash for local charities
Wednesday, July 06, 2022

Two charities reaped $11,000 each thanks to an enduring fundraiser by Hamilton Lions Club.

The proceeds from the club’s 53rd annual Gas-O-Rama and raffle draw were presented to Vision Bermuda and the Bermuda Zoological Society.


Aspen Plants First Red Mangroves on Trunk Island
Wednesday, June 22, 2022

On Friday 3rd June, employees from Aspen were excited to plant the first young red mangrove trees in their sponsored Coastal Red Mangrove Forest on Trunk Island – the Bermuda Zoological Society’s (BZS) ‘Living Classroom’.



About

Governance
About Us
Board of Directors
Contact Us
Newsletter
Latest News
Gift & Bookstore

Contact

General Inquiries

(441) 293-2727

info@bzs.bm


Latest News

All the latest updates and news from the Bermuda Aquarium, Museum, and Zoo, one of Bermuda's leading visitor attractions!

Aquarium roof work on schedule
Royal Gazette
Thursday, January 15, 2015

By Simon Jones
Published Jan 15, 2015 at 8:00 am (Updated Jan 15, 2015 at 3:14 pm)

Click here to see an Aquarium update from Dr. Ian Walker, Principal Curator at th Bermuda Aquarium, Museum & Zoo.

Work on the aquarium’s new roof is over halfway complete and the project remains well on track, according to Dr Ian Walker.

The Curator of the Bermuda Aquarium, Museum and Zoo told The Royal Gazette he hoped the major construction work would be completed by March and the main hall would be open to the public again in April.

RG_150115_1a.jpeg
A Sunrise Construction crew member continues work on the roof structure improvements
at the Bermuda Aquarium Museum and Zoo (Photo by Akil Simmons)

RG_150115_1b.jpeg
A crew from Sunrise Construction continue work
on the roof structure improvements at the Bermuda
Aquarium Museum and Zoo (Photo by Akil Simmons)

Dr Walker admitted there had been a drop-off in visitors since Christmas, and suggested that it could be because many people mistakenly believed that the aquarium was closed.

“We are very much open,” he said. “The only part of the aquarium and zoo that is closed is the main hall that housed the majority of the fish tanks. These animals have been moved behind the scenes while the work continues.

“The Northrock tank is still open and we would urge people to visit as they usually would.”

RG_150115_1c.jpeg
Team effort: A crew from Sunrise Construction work on the roof structure improvements
at the Bermuda Aquarium, Museum and Zoo 
(Photo by Akil Simmons)

RG_150115_1d.jpeg
A crew from Sunrise Construction continue work on the roof structure improvements
at the Bermuda Aquarium Museum and Zoo 
(Photo by Akil Simmons)

The project, which began in October, has involved the complete demolition of the old roof and a series of new steel beams, which will form the frame of the new roof, have already been installed.

Just last week crews from Sunrise Construction began to put the corrugated roofing into place.

RG_150115_1e.jpeg
A crew from Sunrise Construction work in the main hall of
Bermuda Aquarium and Zoo
 (Photo by Akil Simmons)?

RG_150115_1f.jpeg
Construction workers tackle roof repairs at Bermuda Aquarium,
Museum and Zoo
 (Photo by Mark Tatem)?

Dr Walker said: “We are very happy with how the work has progressed.

“We are on schedule and the guys are working seven days a week to get the job done.

“There is still a lot of work to be done even after the roof is completed.

“We hope to be able to start working on the interior of the main hall in February to reinstate the tanks and start putting up new graphics.”